The American Five Year PlanEnergyRow 8

Transmission energized per year, 100 kV and above

3,300 (2011–2020 average)4,100

Anticipatorycircuit-miles

Why this row

The country energized 3,300 circuit-miles of transmission a year within its regions from 2011 to 2020 and 70 a year between them, while the Department of Energy finds that transfer capacity between regions must grow by 25% to 412% by 2035. Utilities have 41,000 miles under construction or in planning for the next ten years. The row holds them to that pipeline: 4,100 miles a year is the plan delivered on schedule. Interregional miles are reported as their own line because that is where the 2011 to 2020 rate was lowest.

The path

20282029203020312032
3,6403,7603,8703,9904,100

linear; 4,100 a year is the ten-year pipeline of 41,000 miles delivered on schedule

Each July 4 the row shows its baseline, this path, the latest official value and a status of ahead, on schedule or behind. As an anticipatory row it reports the public decisions that delayed it.